Real-Time Temperature Control for High Arch Dam Based on Decision Support System

It is important and difficult to control the temperature of mass concrete structure during high arch dam construction.A new method with decision support system is presented for temperature control and crack prevention.It is a database system with functions of data storage,information inquiry,data an...

Full description

Saved in:
Bibliographic Details
Published inTransactions of Tianjin University Vol. 20; no. 2; pp. 118 - 125
Main Author 井向阳 刘杏红 周伟 常晓林
Format Journal Article
LanguageEnglish
Published Heidelberg Tianjin University 01.04.2014
Subjects
Online AccessGet full text
ISSN1006-4982
1995-8196
DOI10.1007/s12209-014-2210-1

Cover

More Information
Summary:It is important and difficult to control the temperature of mass concrete structure during high arch dam construction.A new method with decision support system is presented for temperature control and crack prevention.It is a database system with functions of data storage,information inquiry,data analysis,early warning and resource sharing.Monitoring information during construction can be digitized via this system,and the intelligent analysis and dynamic control of concrete temperature can be conducted.This method has been applied in the construction of the Dagangshan Arch Dam in China and has proven to be very convenient.Based on the decision support of this system and the dynamic adjustment of construction measures,the concrete temperature of this project is well-controlled.
Bibliography:It is important and difficult to control the temperature of mass concrete structure during high arch dam construction.A new method with decision support system is presented for temperature control and crack prevention.It is a database system with functions of data storage,information inquiry,data analysis,early warning and resource sharing.Monitoring information during construction can be digitized via this system,and the intelligent analysis and dynamic control of concrete temperature can be conducted.This method has been applied in the construction of the Dagangshan Arch Dam in China and has proven to be very convenient.Based on the decision support of this system and the dynamic adjustment of construction measures,the concrete temperature of this project is well-controlled.
concrete arch dam; temperature control; decision support system; pipe cooling; monitoring
Jing Xiangyang;Liu Xinghong;Zhou Wei;Chang Xiaolin;State Key Laboratory of Water Resource and Hydropower Engineering Science,Wuhan University;School of Civil and Architectural Engineering,Wuhan University