Models and matheuristics for the unrelated parallel machine scheduling problem with additional resources

•The problem of unrelated parallel machines with an additional resource is considered.•Two mathematical models are proposed: one adapted from the literature, an original one based on strip packing.•Three matheuristic strategies are proposed.•A comprehensive computational and statistical evaluation i...

Full description

Saved in:
Bibliographic Details
Published inEuropean journal of operational research Vol. 260; no. 2; pp. 482 - 493
Main Authors Fanjul-Peyro, Luis, Perea, Federico, Ruiz, Rubén
Format Journal Article
LanguageEnglish
Published Elsevier B.V 16.07.2017
Subjects
Online AccessGet full text
ISSN0377-2217
1872-6860
1872-6860
DOI10.1016/j.ejor.2017.01.002

Cover

Abstract •The problem of unrelated parallel machines with an additional resource is considered.•Two mathematical models are proposed: one adapted from the literature, an original one based on strip packing.•Three matheuristic strategies are proposed.•A comprehensive computational and statistical evaluation is carried out.•The model based on strip packing is shown to outperform the model adapted from the literature.•Matheuristic strategies are able to solve larger problems more efficiently and effectively. In this paper we analyze a parallel machine scheduling problem in which the processing of jobs on the machines requires a number of units of a scarce resource. This number depends both on the job and on the machine. The availability of resources is limited and fixed throughout the production horizon. The objective considered is the minimization of the makespan. We model this problem by means of two integer linear programming problems. One of them is based on a model previously proposed in the literature. The other one, which is based on the resemblance to strip packing problems, is an original contribution of this paper. As the models presented are incapable of solving medium-sized instances to optimality, we propose three matheuristic strategies for each of these two models. The algorithms proposed are tested over an extensive computational experience. Results show that the matheuristic strategies significantly outperform the mathematical models.
AbstractList •The problem of unrelated parallel machines with an additional resource is considered.•Two mathematical models are proposed: one adapted from the literature, an original one based on strip packing.•Three matheuristic strategies are proposed.•A comprehensive computational and statistical evaluation is carried out.•The model based on strip packing is shown to outperform the model adapted from the literature.•Matheuristic strategies are able to solve larger problems more efficiently and effectively. In this paper we analyze a parallel machine scheduling problem in which the processing of jobs on the machines requires a number of units of a scarce resource. This number depends both on the job and on the machine. The availability of resources is limited and fixed throughout the production horizon. The objective considered is the minimization of the makespan. We model this problem by means of two integer linear programming problems. One of them is based on a model previously proposed in the literature. The other one, which is based on the resemblance to strip packing problems, is an original contribution of this paper. As the models presented are incapable of solving medium-sized instances to optimality, we propose three matheuristic strategies for each of these two models. The algorithms proposed are tested over an extensive computational experience. Results show that the matheuristic strategies significantly outperform the mathematical models.
Author Perea, Federico
Ruiz, Rubén
Fanjul-Peyro, Luis
Author_xml – sequence: 1
  givenname: Luis
  orcidid: 0000-0002-0124-132X
  surname: Fanjul-Peyro
  fullname: Fanjul-Peyro, Luis
  email: lfpeyro@hotmail.com
– sequence: 2
  givenname: Federico
  surname: Perea
  fullname: Perea, Federico
  email: perea@eio.upv.es
– sequence: 3
  givenname: Rubén
  surname: Ruiz
  fullname: Ruiz, Rubén
  email: rruiz@eio.upv.es
BookMark eNqNkEtLxDAQgIMouD7-gKf8gdaZ1jZd8CLiCxQveg5pMrVZssmSpC7-e7usJw8iDAwD883jO2GHPnhi7AKhRMD2clXSKsSyAhQlYAlQHbAFdqIq2q6FQ7aAWoiiqlAcs5OUVgCADTYLNr4EQy5x5Q1fqzzSFG3KVic-hMjnmk8-klOZDN-oqJwjNzfq0XriSY9kJmf9B9_E0Dta863NI1fG2GyDV45HSmGKmtIZOxqUS3T-k0_Z-_3d2-1j8fz68HR781zoeilyQVqo3rSKTN8Y7JqrTrcdDI0SWiyvln0NuqmNrhGX1VDNDaJBjXM0BF0PWJ-yej938hv1tZ0Plpto1yp-SQS5kyVXcidL7mRJQDnLmqluT-kYUoo0SG2z2v2Qo7Lub7T6hf5r3_Uemt3Tp6Uok7bkNRkbSWdpgv0L_wZr9Zqi
CitedBy_id crossref_primary_10_1109_TSM_2023_3304517
crossref_primary_10_1155_2021_5566002
crossref_primary_10_1016_j_cor_2020_105162
crossref_primary_10_1016_j_cor_2024_106777
crossref_primary_10_1177_0954405420928691
crossref_primary_10_1016_j_eswa_2022_117577
crossref_primary_10_1590_0101_7438_2020_040_00218849
crossref_primary_10_1016_j_cor_2019_06_007
crossref_primary_10_1016_j_ins_2018_09_019
crossref_primary_10_1016_j_tre_2024_103826
crossref_primary_10_1016_j_knosys_2019_02_005
crossref_primary_10_1287_ijoc_2021_1113
crossref_primary_10_1016_j_cor_2022_106010
crossref_primary_10_1016_j_ejco_2022_100034
crossref_primary_10_1007_s10845_020_01597_8
crossref_primary_10_1016_j_ejor_2017_10_064
crossref_primary_10_1007_s12063_021_00233_9
crossref_primary_10_3390_sym12091460
crossref_primary_10_3233_JIFS_213473
crossref_primary_10_1007_s10479_019_03212_3
crossref_primary_10_35341_afet_1267389
crossref_primary_10_1016_j_cie_2024_110290
crossref_primary_10_1016_j_ejor_2022_03_045
crossref_primary_10_1016_j_cor_2018_12_016
crossref_primary_10_1016_j_eswa_2019_112959
crossref_primary_10_3390_math9222955
crossref_primary_10_1007_s10951_024_00809_w
crossref_primary_10_1016_j_jclepro_2019_119428
crossref_primary_10_1016_j_ejor_2018_05_056
crossref_primary_10_1049_cim2_12120
crossref_primary_10_1016_j_cie_2024_109900
crossref_primary_10_3390_jmse11081505
crossref_primary_10_47495_okufbed_779834
crossref_primary_10_1007_s11227_025_07030_2
crossref_primary_10_1016_j_ejor_2024_08_011
crossref_primary_10_1016_j_cor_2021_105625
crossref_primary_10_1080_00207543_2019_1661539
crossref_primary_10_1016_j_ejor_2024_08_010
crossref_primary_10_3390_s22082844
crossref_primary_10_1016_j_cor_2018_04_021
crossref_primary_10_1080_00207543_2020_1777481
crossref_primary_10_1007_s11750_020_00589_4
crossref_primary_10_1016_j_eswa_2017_09_054
crossref_primary_10_1016_j_eswax_2020_100022
crossref_primary_10_1016_j_cor_2023_106192
crossref_primary_10_1007_s10878_020_00607_y
crossref_primary_10_1007_s10479_022_05117_0
crossref_primary_10_1016_j_cie_2020_106939
crossref_primary_10_1016_j_cor_2023_106504
crossref_primary_10_3390_designs9020026
crossref_primary_10_1080_00207543_2021_1885068
crossref_primary_10_1007_s11750_018_00494_x
crossref_primary_10_3390_sym14071380
crossref_primary_10_1007_s11750_020_00574_x
crossref_primary_10_3390_app14156736
crossref_primary_10_1007_s10100_019_00655_8
crossref_primary_10_1080_00207543_2022_2121869
crossref_primary_10_1007_s10479_024_05938_1
crossref_primary_10_1016_j_jmsy_2020_06_006
crossref_primary_10_1080_01605682_2017_1415645
crossref_primary_10_1007_s40314_019_0789_5
crossref_primary_10_1016_j_asoc_2024_111694
crossref_primary_10_1080_21681015_2023_2167875
crossref_primary_10_1080_00207543_2022_2135629
crossref_primary_10_1016_j_ejor_2024_07_030
crossref_primary_10_1080_00207543_2020_1781278
crossref_primary_10_1109_TVT_2020_3046304
crossref_primary_10_1007_s11227_020_03516_3
crossref_primary_10_1016_j_cor_2018_07_007
crossref_primary_10_1080_01605682_2023_2233555
crossref_primary_10_1007_s10479_024_06283_z
crossref_primary_10_3390_systems12020037
crossref_primary_10_1007_s11750_021_00610_4
crossref_primary_10_1007_s10951_021_00718_2
crossref_primary_10_1109_TII_2020_3012162
crossref_primary_10_1016_j_cie_2024_110086
crossref_primary_10_1007_s10729_023_09642_7
crossref_primary_10_1109_ACCESS_2018_2872110
crossref_primary_10_1007_s10462_022_10247_9
crossref_primary_10_1016_j_cor_2022_105936
crossref_primary_10_1016_j_omega_2021_102581
crossref_primary_10_1016_j_promfg_2020_01_451
crossref_primary_10_1109_TSMC_2018_2799740
crossref_primary_10_1016_j_ejor_2025_03_022
crossref_primary_10_32604_cmc_2024_054473
crossref_primary_10_1016_j_asoc_2021_107521
crossref_primary_10_1109_ACCESS_2018_2840512
crossref_primary_10_3390_math10142431
crossref_primary_10_1177_1687814019898347
crossref_primary_10_1007_s10489_022_04097_9
crossref_primary_10_1016_j_cor_2021_105308
crossref_primary_10_1016_j_cor_2022_105704
crossref_primary_10_1016_j_ijpe_2023_108977
crossref_primary_10_1080_00207543_2017_1421781
crossref_primary_10_1016_j_cie_2020_106505
crossref_primary_10_25077_josi_v21_n2_p97_105_2022
crossref_primary_10_1016_j_knosys_2022_108193
crossref_primary_10_1016_j_omega_2021_102431
crossref_primary_10_1016_j_apm_2021_01_017
crossref_primary_10_1016_j_omega_2021_102432
crossref_primary_10_1016_j_swevo_2021_101016
crossref_primary_10_1080_00207543_2024_2334419
crossref_primary_10_1016_j_ejor_2020_10_052
crossref_primary_10_1155_2021_8166343
crossref_primary_10_17341_gazimmfd_1099034
crossref_primary_10_1016_j_cor_2020_105115
crossref_primary_10_1016_j_cor_2024_106968
crossref_primary_10_1016_j_cie_2024_110261
crossref_primary_10_3390_sym16020203
crossref_primary_10_1007_s12597_022_00587_z
crossref_primary_10_1016_j_cie_2024_110828
crossref_primary_10_1016_j_cor_2019_07_016
crossref_primary_10_1080_00207543_2019_1672900
Cites_doi 10.1016/j.ejor.2015.04.004
10.1023/A:1021569406280
10.1007/s00170-011-3454-8
10.1016/j.orl.2007.08.001
10.1007/s10951-015-0422-4
10.1016/S0166-218X(96)00087-X
10.1016/0166-218X(83)90012-4
10.1016/j.ejor.2010.03.030
10.1016/S0166-218X(03)00433-5
10.1007/BF00263292
10.1016/S0377-2217(02)00246-1
10.1080/07408170008963887
10.1016/S0305-0548(98)00054-9
10.1109/TAES.2011.5937273
10.1016/j.ejor.2013.02.042
10.1007/s10107-006-0059-3
10.1016/j.ejor.2004.04.015
10.1080/03052151003759117
10.1016/j.cor.2013.11.016
10.1007/s10951-011-0231-3
10.1111/itor.12103
10.1016/S0167-5060(08)70743-X
10.1016/j.cor.2010.05.005
10.1016/S0377-2217(02)00123-6
10.1287/mnsc.6.1.1
10.1016/j.ejor.2014.11.036
10.1007/978-3-642-21311-3_10
10.1016/j.cie.2012.03.018
ContentType Journal Article
Copyright 2017 Elsevier B.V.
Copyright_xml – notice: 2017 Elsevier B.V.
DBID AAYXX
CITATION
ADTOC
UNPAY
DOI 10.1016/j.ejor.2017.01.002
DatabaseName CrossRef
Unpaywall for CDI: Periodical Content
Unpaywall
DatabaseTitle CrossRef
DatabaseTitleList
Database_xml – sequence: 1
  dbid: UNPAY
  name: Unpaywall
  url: https://proxy.k.utb.cz/login?url=https://unpaywall.org/
  sourceTypes: Open Access Repository
DeliveryMethod fulltext_linktorsrc
Discipline Engineering
Computer Science
Business
EISSN 1872-6860
EndPage 493
ExternalDocumentID 10.1016/j.ejor.2017.01.002
10_1016_j_ejor_2017_01_002
S0377221717300073
GroupedDBID --K
--M
-~X
.DC
.~1
0R~
1B1
1RT
1~.
1~5
4.4
457
4G.
5GY
5VS
6OB
7-5
71M
8P~
9JN
9JO
AAAKF
AABNK
AACTN
AAEDT
AAEDW
AAIAV
AAIKJ
AAKOC
AALRI
AAOAW
AAQFI
AARIN
AAXUO
AAYFN
ABAOU
ABBOA
ABFNM
ABFRF
ABJNI
ABMAC
ABUCO
ABYKQ
ACAZW
ACDAQ
ACGFO
ACGFS
ACIWK
ACNCT
ACRLP
ACZNC
ADBBV
ADEZE
ADGUI
AEBSH
AEFWE
AEKER
AENEX
AFKWA
AFTJW
AGHFR
AGUBO
AGYEJ
AHHHB
AHZHX
AIALX
AIEXJ
AIGVJ
AIKHN
AITUG
AJBFU
AJOXV
ALMA_UNASSIGNED_HOLDINGS
AMFUW
AMRAJ
AOUOD
APLSM
ARUGR
AXJTR
BKOJK
BKOMP
BLXMC
CS3
DU5
EBS
EFJIC
EFLBG
EJD
EO8
EO9
EP2
EP3
F5P
FDB
FIRID
FNPLU
FYGXN
G-Q
GBLVA
GBOLZ
HAMUX
IHE
J1W
KOM
LY1
M41
MHUIS
MO0
MS~
N9A
O-L
O9-
OAUVE
OZT
P-8
P-9
P2P
PC.
PQQKQ
Q38
RIG
ROL
RPZ
RXW
SCC
SDF
SDG
SDP
SDS
SES
SPC
SPCBC
SSB
SSD
SSV
SSW
SSZ
T5K
TAE
TN5
U5U
XPP
ZMT
~02
~G-
1OL
29G
41~
AAAKG
AAQXK
AATTM
AAXKI
AAYWO
AAYXX
ABWVN
ABXDB
ACLOT
ACNNM
ACRPL
ACVFH
ADCNI
ADIYS
ADJOM
ADMUD
ADNMO
ADXHL
AEIPS
AEUPX
AFFNX
AFJKZ
AFPUW
AGQPQ
AI.
AIGII
AIIUN
AKBMS
AKRWK
AKYEP
ANKPU
APXCP
ASPBG
AVWKF
AZFZN
CITATION
EFKBS
FEDTE
FGOYB
HVGLF
HZ~
R2-
SEW
VH1
WUQ
~HD
ADTOC
UNPAY
ID FETCH-LOGICAL-c397t-ec7abd6aedb5d18548c680f5a7c7949b30c53dc31192f2185751c11c15e08b013
IEDL.DBID .~1
ISSN 0377-2217
1872-6860
IngestDate Sun Oct 26 04:16:13 EDT 2025
Wed Oct 01 04:08:33 EDT 2025
Thu Apr 24 23:13:16 EDT 2025
Fri Feb 23 02:27:38 EST 2024
IsDoiOpenAccess true
IsOpenAccess true
IsPeerReviewed true
IsScholarly true
Issue 2
Keywords Parallel machine problem
Scheduling
Makespan
Additional resources
Matheuristics
Language English
LinkModel DirectLink
MergedId FETCHMERGED-LOGICAL-c397t-ec7abd6aedb5d18548c680f5a7c7949b30c53dc31192f2185751c11c15e08b013
ORCID 0000-0002-0124-132X
OpenAccessLink https://proxy.k.utb.cz/login?url=https://www.sciencedirect.com/science/article/pii/S0377221717300073
PageCount 12
ParticipantIDs unpaywall_primary_10_1016_j_ejor_2017_01_002
crossref_citationtrail_10_1016_j_ejor_2017_01_002
crossref_primary_10_1016_j_ejor_2017_01_002
elsevier_sciencedirect_doi_10_1016_j_ejor_2017_01_002
ProviderPackageCode CITATION
AAYXX
PublicationCentury 2000
PublicationDate 2017-07-16
PublicationDateYYYYMMDD 2017-07-16
PublicationDate_xml – month: 07
  year: 2017
  text: 2017-07-16
  day: 16
PublicationDecade 2010
PublicationTitle European journal of operational research
PublicationYear 2017
Publisher Elsevier B.V
Publisher_xml – name: Elsevier B.V
References Lodi, Martello, Monaci (bib0023) 2002; 141
Perea, de Waard (bib0027) 2011; 47
Billaut, Croce, Grosso (bib0002) 2015; 243
Błażewicz, Kubiak, Röck, Szwarcfiter (bib0004) 1987; 24
Daniels, Hua, Webster (bib0007) 1999; 26
Edis, Oguz (bib0009) 2012; 63
Fanjul-Peyro, Ruiz (bib0013) 2010; 207
Stefanello, de Araújo, Müller (bib0031) 2015; 22
Kravchenko, Werner (bib0021) 2011; 14
Croce, Salassa, T’kindt (bib0006) 2014; 45
Kellerer, Strusevich (bib0020) 2003; 133
Sule (bib0032) 2008
Mokotoff, Jimeno (bib0026) 2002; 117
Kellerer, Strusevich (bib0019) 2003; 147
Edis, Oguz (bib0008) 2011; vol. 6697
Ventura, Daecheol (bib0034) 2000; 32
Grigoriev, Sviridenko, Uetz (bib0016) 2005; Vol. 3509
Grigoriev, Sviridenko, Uetz (bib0017) 2007; 110
Toffolo, Santos, Carvalho, Soares (bib0033) 2015; 19
Ghirardi, Potts (bib0015) 2005; 165
Błażewicz, Lenstra, Rinnooy Kan (bib0005) 1983; 5
Allahverdi (bib0001) 2015; 246
Fanjul-Peyro, Ruiz (bib0014) 2011; 38
Pinedo (bib0029) 2016
Edis, Oguz, Ozkarahan (bib0010) 2013; 230
Błażewicz, Ecker, Pesch, Schmidt, Weglarz (bib0003) 2007
Edis, Ozkarahan (bib0012) 2012; 9
Pinedo (bib0028) 2005
Kellerer (bib0018) 2008; 36
Martello, Soumis, Toth (bib0024) 1997; 75
Edis, Ozkarahan (bib0011) 2011; 43
McNaughton (bib0025) 1959; 6
Słowiński (bib0030) 1980; 31
Lenstra, Rinnooy Kan, Brucker (bib0022) 1977; 1
Grigoriev (10.1016/j.ejor.2017.01.002_bib0017) 2007; 110
Martello (10.1016/j.ejor.2017.01.002_bib0024) 1997; 75
Pinedo (10.1016/j.ejor.2017.01.002_bib0029) 2016
Sule (10.1016/j.ejor.2017.01.002_bib0032) 2008
Błażewicz (10.1016/j.ejor.2017.01.002_bib0004) 1987; 24
Słowiński (10.1016/j.ejor.2017.01.002_bib0030) 1980; 31
Edis (10.1016/j.ejor.2017.01.002_bib0011) 2011; 43
Billaut (10.1016/j.ejor.2017.01.002_bib0002) 2015; 243
Kellerer (10.1016/j.ejor.2017.01.002_bib0020) 2003; 133
Błażewicz (10.1016/j.ejor.2017.01.002_bib0005) 1983; 5
Toffolo (10.1016/j.ejor.2017.01.002_bib0033) 2015; 19
Edis (10.1016/j.ejor.2017.01.002_bib0008) 2011; vol. 6697
Daniels (10.1016/j.ejor.2017.01.002_bib0007) 1999; 26
Fanjul-Peyro (10.1016/j.ejor.2017.01.002_bib0013) 2010; 207
Kravchenko (10.1016/j.ejor.2017.01.002_bib0021) 2011; 14
Kellerer (10.1016/j.ejor.2017.01.002_bib0018) 2008; 36
Grigoriev (10.1016/j.ejor.2017.01.002_bib0016) 2005; Vol. 3509
Ventura (10.1016/j.ejor.2017.01.002_bib0034) 2000; 32
Allahverdi (10.1016/j.ejor.2017.01.002_bib0001) 2015; 246
Lenstra (10.1016/j.ejor.2017.01.002_bib0022) 1977; 1
Edis (10.1016/j.ejor.2017.01.002_bib0009) 2012; 63
Edis (10.1016/j.ejor.2017.01.002_bib0010) 2013; 230
Edis (10.1016/j.ejor.2017.01.002_bib0012) 2012; 9
Ghirardi (10.1016/j.ejor.2017.01.002_bib0015) 2005; 165
Lodi (10.1016/j.ejor.2017.01.002_bib0023) 2002; 141
Croce (10.1016/j.ejor.2017.01.002_bib0006) 2014; 45
Kellerer (10.1016/j.ejor.2017.01.002_bib0019) 2003; 147
Pinedo (10.1016/j.ejor.2017.01.002_bib0028) 2005
McNaughton (10.1016/j.ejor.2017.01.002_bib0025) 1959; 6
Perea (10.1016/j.ejor.2017.01.002_bib0027) 2011; 47
Błażewicz (10.1016/j.ejor.2017.01.002_bib0003) 2007
Mokotoff (10.1016/j.ejor.2017.01.002_bib0026) 2002; 117
Stefanello (10.1016/j.ejor.2017.01.002_bib0031) 2015; 22
Fanjul-Peyro (10.1016/j.ejor.2017.01.002_bib0014) 2011; 38
References_xml – volume: 243
  start-page: 75
  year: 2015
  end-page: 81
  ident: bib0002
  article-title: A single machine scheduling problem with two-dimensional vector packing constraints
  publication-title: European Journal of Operational Research
– volume: 36
  start-page: 157
  year: 2008
  end-page: 159
  ident: bib0018
  article-title: An approximation algorithm for identical parallel machine scheduling with resource dependent processing times
  publication-title: Operations Research Letters
– volume: 31
  start-page: 711
  year: 1980
  end-page: 723
  ident: bib0030
  article-title: Two approaches to problems of resource allocation among project activities, a comparative study
  publication-title: Journal of the Operational Research Society
– volume: 14
  start-page: 435
  year: 2011
  end-page: 444
  ident: bib0021
  article-title: Parallel machine problems with equal processing times: A survey
  publication-title: Journal of Scheduling
– volume: 117
  start-page: 133
  year: 2002
  end-page: 150
  ident: bib0026
  article-title: Heuristics based on partial enumeration for the unrelated parallel processor scheduling problem
  publication-title: Annals of Operations Research
– volume: 22
  start-page: 149
  year: 2015
  end-page: 167
  ident: bib0031
  article-title: Matheuristics for the capacitated p-median problem
  publication-title: International Transactions in Operational Research
– volume: 6
  start-page: 1
  year: 1959
  end-page: 12
  ident: bib0025
  article-title: Scheduling with deadlines and loss functions
  publication-title: Management Science
– volume: 26
  start-page: 143
  year: 1999
  end-page: 155
  ident: bib0007
  article-title: Heuristics for parallel-machine flexible-resource scheduling problems with unspecified job assignment
  publication-title: Computers & Operations Research
– volume: 246
  start-page: 345
  year: 2015
  end-page: 378
  ident: bib0001
  article-title: The third comprehensive survey on scheduling problems with setup times/costs
  publication-title: European Journal of Operational Research
– volume: 207
  start-page: 55
  year: 2010
  end-page: 69
  ident: bib0013
  article-title: Iterated greedy local search methods for unrelated parallel machine scheduling
  publication-title: European Journal of Operational Research
– volume: 133
  start-page: 45
  year: 2003
  end-page: 68
  ident: bib0020
  article-title: Scheduling problems for parallel dedicated machines under multiple resource constraints
  publication-title: Discrete Applied Mathematics
– year: 2008
  ident: bib0032
  publication-title: Production planning and industrial scheduling: examples, case studies and applications
– volume: 19
  start-page: 295
  year: 2015
  end-page: 307
  ident: bib0033
  article-title: An integer programming approach to the multimode resource-constrained multiproject scheduling problem
  publication-title: Journal of Scheduling
– year: 2005
  ident: bib0028
  article-title: Planning and scheduling in manufacturing and services
  publication-title: Springer series in operations research
– volume: 75
  start-page: 169
  year: 1997
  end-page: 188
  ident: bib0024
  article-title: Exact and approximation algorithms for makespan minimization on unrelated parallel machines
  publication-title: Discrete Applied Mathematics
– volume: 110
  start-page: 209
  year: 2007
  end-page: 228
  ident: bib0017
  article-title: Machine scheduling with resource dependent processing times
  publication-title: Mathematical Programming Series B
– volume: 45
  start-page: 7
  year: 2014
  end-page: 11
  ident: bib0006
  article-title: A hybrid heuristic approach for single machine scheduling with release times
  publication-title: Computers & Operations Research
– volume: 1
  start-page: 343
  year: 1977
  end-page: 362
  ident: bib0022
  article-title: Complexity of machine scheduling problems
  publication-title: Annals of Discrete Mathematics
– volume: 32
  start-page: 147
  year: 2000
  end-page: 153
  ident: bib0034
  article-title: Parallel machine scheduling about an unrestricted due date and additional resource constraints
  publication-title: IIE Transactions
– volume: 24
  start-page: 513
  year: 1987
  end-page: 524
  ident: bib0004
  article-title: Minimizing mean flow-time with parallel processors and resource constraints
  publication-title: Acta Informatica
– year: 2007
  ident: bib0003
  publication-title: Handbook on scheduling
– volume: 47
  start-page: 1915
  year: 2011
  end-page: 1925
  ident: bib0027
  article-title: Greedy and k-greedy algorithms for multidimensional data association
  publication-title: IEEE Transactions on Aerospace and Electronic Systems
– volume: 43
  start-page: 135
  year: 2011
  end-page: 157
  ident: bib0011
  article-title: A combined integer/constraint programming approach to a resource-constrained parallel machine scheduling problem with machine eligibility restrictions
  publication-title: Engineering Optimization
– year: 2016
  ident: bib0029
  publication-title: Scheduling: Theory, algorithms and systems
– volume: 63
  start-page: 433
  year: 2012
  end-page: 447
  ident: bib0009
  article-title: Parallel machine scheduling with flexible resources
  publication-title: Computers and Industrial Engineering
– volume: 147
  start-page: 345
  year: 2003
  end-page: 364
  ident: bib0019
  article-title: Scheduling parallel dedicated machines under a single non-shared resource
  publication-title: European Journal of Operational Research
– volume: vol. 6697
  start-page: 92
  year: 2011
  end-page: 98
  ident: bib0008
  article-title: Parallel machine scheduling with additional resources: A Lagrangian-based constraint programming approach
  publication-title: Lecture notes in computer science, CPAIOR 2011
– volume: 141
  start-page: 241
  year: 2002
  end-page: 252
  ident: bib0023
  article-title: Two-dimensional packing problems: A survey
  publication-title: European Journal of Operational Research
– volume: 38
  start-page: 301
  year: 2011
  end-page: 309
  ident: bib0014
  article-title: Size-reduction heuristics for the unrelated parallel machines scheduling problem
  publication-title: Computers & Operations Research
– volume: 230
  start-page: 449
  year: 2013
  end-page: 463
  ident: bib0010
  article-title: Parallel machine scheduling with additional resources: Notation, classification, models and solution methods
  publication-title: European Journal of Operational Research
– volume: 5
  start-page: 11
  year: 1983
  end-page: 24
  ident: bib0005
  article-title: Scheduling subject to resource constraints: classification and complexity
  publication-title: Discrete Applied Mathematics
– volume: 9
  start-page: 1141
  year: 2012
  end-page: 1153
  ident: bib0012
  article-title: Solution approaches for a real-life resource constrained parallel machine scheduling problem
  publication-title: International Journal of Advanced Manufacturing Technology
– volume: 165
  start-page: 457
  year: 2005
  end-page: 467
  ident: bib0015
  article-title: Makespan minimization for scheduling unrelated parallel machines: A recovering beam search approach
  publication-title: European Journal of Operational Research
– volume: Vol. 3509
  start-page: 182
  year: 2005
  end-page: 195
  ident: bib0016
  article-title: Unrelated parallel machine scheduling with resource dependent processing
  publication-title: TIMES, Proceedings of the 11th conference on integer programming and combinatorial optimization
– volume: 246
  start-page: 345
  issue: 2
  year: 2015
  ident: 10.1016/j.ejor.2017.01.002_bib0001
  article-title: The third comprehensive survey on scheduling problems with setup times/costs
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2015.04.004
– volume: 117
  start-page: 133
  issue: 1–4
  year: 2002
  ident: 10.1016/j.ejor.2017.01.002_bib0026
  article-title: Heuristics based on partial enumeration for the unrelated parallel processor scheduling problem
  publication-title: Annals of Operations Research
  doi: 10.1023/A:1021569406280
– year: 2005
  ident: 10.1016/j.ejor.2017.01.002_bib0028
  article-title: Planning and scheduling in manufacturing and services
– volume: 9
  start-page: 1141
  issue: 12
  year: 2012
  ident: 10.1016/j.ejor.2017.01.002_bib0012
  article-title: Solution approaches for a real-life resource constrained parallel machine scheduling problem
  publication-title: International Journal of Advanced Manufacturing Technology
  doi: 10.1007/s00170-011-3454-8
– volume: 36
  start-page: 157
  issue: 2
  year: 2008
  ident: 10.1016/j.ejor.2017.01.002_bib0018
  article-title: An approximation algorithm for identical parallel machine scheduling with resource dependent processing times
  publication-title: Operations Research Letters
  doi: 10.1016/j.orl.2007.08.001
– volume: 19
  start-page: 295
  issue: 3
  year: 2015
  ident: 10.1016/j.ejor.2017.01.002_bib0033
  article-title: An integer programming approach to the multimode resource-constrained multiproject scheduling problem
  publication-title: Journal of Scheduling
  doi: 10.1007/s10951-015-0422-4
– volume: 75
  start-page: 169
  issue: 2
  year: 1997
  ident: 10.1016/j.ejor.2017.01.002_bib0024
  article-title: Exact and approximation algorithms for makespan minimization on unrelated parallel machines
  publication-title: Discrete Applied Mathematics
  doi: 10.1016/S0166-218X(96)00087-X
– volume: 5
  start-page: 11
  issue: 1
  year: 1983
  ident: 10.1016/j.ejor.2017.01.002_bib0005
  article-title: Scheduling subject to resource constraints: classification and complexity
  publication-title: Discrete Applied Mathematics
  doi: 10.1016/0166-218X(83)90012-4
– volume: 207
  start-page: 55
  issue: 1
  year: 2010
  ident: 10.1016/j.ejor.2017.01.002_bib0013
  article-title: Iterated greedy local search methods for unrelated parallel machine scheduling
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2010.03.030
– year: 2016
  ident: 10.1016/j.ejor.2017.01.002_bib0029
– volume: 133
  start-page: 45
  issue: 1–3
  year: 2003
  ident: 10.1016/j.ejor.2017.01.002_bib0020
  article-title: Scheduling problems for parallel dedicated machines under multiple resource constraints
  publication-title: Discrete Applied Mathematics
  doi: 10.1016/S0166-218X(03)00433-5
– volume: 31
  start-page: 711
  issue: 8
  year: 1980
  ident: 10.1016/j.ejor.2017.01.002_bib0030
  article-title: Two approaches to problems of resource allocation among project activities, a comparative study
  publication-title: Journal of the Operational Research Society
– volume: 24
  start-page: 513
  issue: 5
  year: 1987
  ident: 10.1016/j.ejor.2017.01.002_bib0004
  article-title: Minimizing mean flow-time with parallel processors and resource constraints
  publication-title: Acta Informatica
  doi: 10.1007/BF00263292
– volume: 147
  start-page: 345
  issue: 2
  year: 2003
  ident: 10.1016/j.ejor.2017.01.002_bib0019
  article-title: Scheduling parallel dedicated machines under a single non-shared resource
  publication-title: European Journal of Operational Research
  doi: 10.1016/S0377-2217(02)00246-1
– year: 2007
  ident: 10.1016/j.ejor.2017.01.002_bib0003
– volume: Vol. 3509
  start-page: 182
  year: 2005
  ident: 10.1016/j.ejor.2017.01.002_bib0016
  article-title: Unrelated parallel machine scheduling with resource dependent processing
– volume: 32
  start-page: 147
  issue: 2
  year: 2000
  ident: 10.1016/j.ejor.2017.01.002_bib0034
  article-title: Parallel machine scheduling about an unrestricted due date and additional resource constraints
  publication-title: IIE Transactions
  doi: 10.1080/07408170008963887
– volume: 26
  start-page: 143
  issue: 2
  year: 1999
  ident: 10.1016/j.ejor.2017.01.002_bib0007
  article-title: Heuristics for parallel-machine flexible-resource scheduling problems with unspecified job assignment
  publication-title: Computers & Operations Research
  doi: 10.1016/S0305-0548(98)00054-9
– volume: 47
  start-page: 1915
  issue: 3
  year: 2011
  ident: 10.1016/j.ejor.2017.01.002_bib0027
  article-title: Greedy and k-greedy algorithms for multidimensional data association
  publication-title: IEEE Transactions on Aerospace and Electronic Systems
  doi: 10.1109/TAES.2011.5937273
– volume: 230
  start-page: 449
  issue: 3
  year: 2013
  ident: 10.1016/j.ejor.2017.01.002_bib0010
  article-title: Parallel machine scheduling with additional resources: Notation, classification, models and solution methods
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2013.02.042
– volume: 110
  start-page: 209
  issue: 1
  year: 2007
  ident: 10.1016/j.ejor.2017.01.002_bib0017
  article-title: Machine scheduling with resource dependent processing times
  publication-title: Mathematical Programming Series B
  doi: 10.1007/s10107-006-0059-3
– volume: 165
  start-page: 457
  issue: 2
  year: 2005
  ident: 10.1016/j.ejor.2017.01.002_bib0015
  article-title: Makespan minimization for scheduling unrelated parallel machines: A recovering beam search approach
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2004.04.015
– volume: 43
  start-page: 135
  issue: 2
  year: 2011
  ident: 10.1016/j.ejor.2017.01.002_bib0011
  article-title: A combined integer/constraint programming approach to a resource-constrained parallel machine scheduling problem with machine eligibility restrictions
  publication-title: Engineering Optimization
  doi: 10.1080/03052151003759117
– year: 2008
  ident: 10.1016/j.ejor.2017.01.002_bib0032
– volume: 45
  start-page: 7
  year: 2014
  ident: 10.1016/j.ejor.2017.01.002_bib0006
  article-title: A hybrid heuristic approach for single machine scheduling with release times
  publication-title: Computers & Operations Research
  doi: 10.1016/j.cor.2013.11.016
– volume: 14
  start-page: 435
  issue: 5
  year: 2011
  ident: 10.1016/j.ejor.2017.01.002_bib0021
  article-title: Parallel machine problems with equal processing times: A survey
  publication-title: Journal of Scheduling
  doi: 10.1007/s10951-011-0231-3
– volume: 22
  start-page: 149
  issue: 1
  year: 2015
  ident: 10.1016/j.ejor.2017.01.002_bib0031
  article-title: Matheuristics for the capacitated p-median problem
  publication-title: International Transactions in Operational Research
  doi: 10.1111/itor.12103
– volume: 1
  start-page: 343
  year: 1977
  ident: 10.1016/j.ejor.2017.01.002_bib0022
  article-title: Complexity of machine scheduling problems
  publication-title: Annals of Discrete Mathematics
  doi: 10.1016/S0167-5060(08)70743-X
– volume: 38
  start-page: 301
  issue: 1
  year: 2011
  ident: 10.1016/j.ejor.2017.01.002_bib0014
  article-title: Size-reduction heuristics for the unrelated parallel machines scheduling problem
  publication-title: Computers & Operations Research
  doi: 10.1016/j.cor.2010.05.005
– volume: 141
  start-page: 241
  issue: 2
  year: 2002
  ident: 10.1016/j.ejor.2017.01.002_bib0023
  article-title: Two-dimensional packing problems: A survey
  publication-title: European Journal of Operational Research
  doi: 10.1016/S0377-2217(02)00123-6
– volume: 6
  start-page: 1
  issue: 1
  year: 1959
  ident: 10.1016/j.ejor.2017.01.002_bib0025
  article-title: Scheduling with deadlines and loss functions
  publication-title: Management Science
  doi: 10.1287/mnsc.6.1.1
– volume: 243
  start-page: 75
  issue: 1
  year: 2015
  ident: 10.1016/j.ejor.2017.01.002_bib0002
  article-title: A single machine scheduling problem with two-dimensional vector packing constraints
  publication-title: European Journal of Operational Research
  doi: 10.1016/j.ejor.2014.11.036
– volume: vol. 6697
  start-page: 92
  year: 2011
  ident: 10.1016/j.ejor.2017.01.002_bib0008
  article-title: Parallel machine scheduling with additional resources: A Lagrangian-based constraint programming approach
  doi: 10.1007/978-3-642-21311-3_10
– volume: 63
  start-page: 433
  issue: 2
  year: 2012
  ident: 10.1016/j.ejor.2017.01.002_bib0009
  article-title: Parallel machine scheduling with flexible resources
  publication-title: Computers and Industrial Engineering
  doi: 10.1016/j.cie.2012.03.018
SSID ssj0001515
Score 2.5837507
Snippet •The problem of unrelated parallel machines with an additional resource is considered.•Two mathematical models are proposed: one adapted from the literature,...
SourceID unpaywall
crossref
elsevier
SourceType Open Access Repository
Enrichment Source
Index Database
Publisher
StartPage 482
SubjectTerms Additional resources
Makespan
Matheuristics
Parallel machine problem
Scheduling
SummonAdditionalLinks – databaseName: Unpaywall
  dbid: UNPAY
  link: http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwpV1LS8QwEB50BR8HH6vimxy8ad1k2_RxFFFEUARd0FNJkyyu1rroFtFf70ybioqIIvSSMqWPmU6-TGa-Adj2uVZUQ-J1o37XC3QgPCVwyPsclxMyyXjVJeL0LDzuBSdX8moMDppaGEqrdL6_9umVt3ZnOu5rdoaDQeeC-4gMEVELolxHSx2HiVAiIG_BRO_sfP-62j-IIo9kaNkVR10vjEPuSmfqLC97-0CsoCKqyDtdcOWb6WmqLIbq5Vnl-Yfp52gOTPPgddbJ3V45yvb06xdOx3--2TzMOnjK9mu5BRizRRsmm-z4Nsw1XSCYcwptmPlAabgIN9RcLX9iqjDsntBl6aigGaJjhmNWFlX9jDWMaMfz3OYoSBmdluFKG2c-KpBnrtENozgxo6SnOmbJHt12w9MS9I4OLw-OPdfNwdOIeUae1ZHKTKisyaRBlBDEOox5X6pIo09IMrQa6RvtC8Sc_S5RVEmhBR7S8piitcvQKh4KuwIsEdIkIjA688OAmyQLAuUrZTSnsmIZr4JolJhqR3VOHTfytMlpu01J8SkpPuUiRcWvws77NcOa6ONHadnYRvpJqSnORD9et_tuSL-4zdrfxNdhmkYUehbhBrRGj6XdRMw0yrbcP_EGli4VQQ
  priority: 102
  providerName: Unpaywall
Title Models and matheuristics for the unrelated parallel machine scheduling problem with additional resources
URI https://dx.doi.org/10.1016/j.ejor.2017.01.002
https://www.sciencedirect.com/science/article/pii/S0377221717300073
UnpaywallVersion publishedVersion
Volume 260
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
journalDatabaseRights – providerCode: PRVESC
  databaseName: Baden-Württemberg Complete Freedom Collection (Elsevier)
  customDbUrl:
  eissn: 1872-6860
  dateEnd: 99991231
  omitProxy: true
  ssIdentifier: ssj0001515
  issn: 0377-2217
  databaseCode: GBLVA
  dateStart: 20110101
  isFulltext: true
  titleUrlDefault: https://www.sciencedirect.com
  providerName: Elsevier
– providerCode: PRVESC
  databaseName: Elsevier SD Complete Freedom Collection [SCCMFC]
  customDbUrl:
  eissn: 1872-6860
  dateEnd: 99991231
  omitProxy: true
  ssIdentifier: ssj0001515
  issn: 0377-2217
  databaseCode: ACRLP
  dateStart: 19950105
  isFulltext: true
  titleUrlDefault: https://www.sciencedirect.com
  providerName: Elsevier
– providerCode: PRVESC
  databaseName: Elsevier SD Freedom Collection Journals [SCFCJ]
  customDbUrl:
  eissn: 1872-6860
  dateEnd: 99991231
  omitProxy: true
  ssIdentifier: ssj0001515
  issn: 0377-2217
  databaseCode: AIKHN
  dateStart: 19950105
  isFulltext: true
  titleUrlDefault: https://www.sciencedirect.com
  providerName: Elsevier
– providerCode: PRVESC
  databaseName: ScienceDirect (Elsevier)
  customDbUrl:
  eissn: 1872-6860
  dateEnd: 99991231
  omitProxy: true
  ssIdentifier: ssj0001515
  issn: 0377-2217
  databaseCode: .~1
  dateStart: 19950101
  isFulltext: true
  titleUrlDefault: https://www.sciencedirect.com
  providerName: Elsevier
– providerCode: PRVLSH
  databaseName: Elsevier Journals
  customDbUrl:
  mediaType: online
  eissn: 1872-6860
  dateEnd: 99991231
  omitProxy: true
  ssIdentifier: ssj0001515
  issn: 0377-2217
  databaseCode: AKRWK
  dateStart: 19770101
  isFulltext: true
  providerName: Library Specific Holdings
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwnV1LS8QwEB5EwcfBx6r4JgdvWjfZJu32uIiyKi6CLuippEkWlVoX3UW8-NudaVMfICJCoaQkpGSSzJfJzDcAuyE3mmJIglY8aAXSSBFogUU-4HicUEnGyywR572o25en1-p6Ag7rWBhyq_R7f7Wnl7u1_9L0o9kc3t01L3mIyBARtSDKdZypFMEuY8picPD26eZBCru8SYjjgGr7wJnKx8vdPxInqIhL6k5vWvlBOc2Mi6F-fdF5_kX5HC_CvEeNrFP92BJMuKIB07XTegMW6uQMzK_VBsx9YRpchlvKeZY_M11Y9kCgb-wZmhmCVoZlNi7KsBZnGbGB57nLsSI5WjqGB2BUSBS3znz-GUbmW0a-SJUpkT35W4DnFegfH10ddgOfZCEwCEVGgTOxzmyknc2UReUt2yZq84HSscGlmmQoTBVaEwqEgoMWMUcpYQQ-yvE2GVFXYbJ4LNwasEQomwhpTRZGktskk1KHWlvDKdpXtddB1KObGs9ATokw8rR2NbtPSSIpSSTlIkWJrMPeR5thxb_xa21VCy39NotSVBC_ttv_kPAfutn4ZzebMEslMg2LaAsmR09jt42YZpTtlJN2B6Y6J2fdHr77vYvOzTvDQ_gM
linkProvider Elsevier
linkToHtml http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwnV3LS_QwEB98gI-Dj_UTn585eNO6yTZpt0cRZf18XFTwFtIky6fUuugu4sW_3Zk29QEiIvSSNiElk2R-mcz8BmA75tZQDEnUSfudSFopIiOwyPscjxMqy3mVJeLsPOldyX_X6noMDppYGHKrDHt_vadXu3V40w6j2R7c3LQveIzIEBG1IMp1nKnjMClVJ6UT2N7Lu58HaezqKiFNI6oeImdqJy9_e0-koCKtuDuDbeUL7TQ9Kgfm-ckUxQftc7QAcwE2sv36zxZhzJctmGq81lsw32RnYGGxtmD2A9XgEvynpGfFIzOlY3eE-kaBopkhamVYZqOyimvxjhEdeFH4AiuSp6VneAJGjUSB6ywkoGFkv2XkjFTbEtlDuAZ4_ANXR4eXB70oZFmILGKRYeRtanKXGO9y5VB7y65NuryvTGpxrWY5SlPFzsYCsWC_Q9RRSliBj_K8S1bUZZgo70u_AiwTymVCOpvHieQuy6U0sTHOcgr3Vd1VEM3oahsoyCkTRqEbX7NbTRLRJBHNhUaJrMLOW5tBTcDxbW3VCE1_mkYaNcS37XbfJPyDbtZ-2c0WTPcuz0716fH5yTrM0BeyE4tkAyaGDyO_iQBnmP-tJvAru0v38Q
linkToUnpaywall http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwpV1LS8QwEB50BR8HH6vimxy8ad1k2_RxFFFEUARd0FNJkyyu1rroFtFf70ybioqIIvSSMqWPmU6-TGa-Adj2uVZUQ-J1o37XC3QgPCVwyPsclxMyyXjVJeL0LDzuBSdX8moMDppaGEqrdL6_9umVt3ZnOu5rdoaDQeeC-4gMEVELolxHSx2HiVAiIG_BRO_sfP-62j-IIo9kaNkVR10vjEPuSmfqLC97-0CsoCKqyDtdcOWb6WmqLIbq5Vnl-Yfp52gOTPPgddbJ3V45yvb06xdOx3--2TzMOnjK9mu5BRizRRsmm-z4Nsw1XSCYcwptmPlAabgIN9RcLX9iqjDsntBl6aigGaJjhmNWFlX9jDWMaMfz3OYoSBmdluFKG2c-KpBnrtENozgxo6SnOmbJHt12w9MS9I4OLw-OPdfNwdOIeUae1ZHKTKisyaRBlBDEOox5X6pIo09IMrQa6RvtC8Sc_S5RVEmhBR7S8piitcvQKh4KuwIsEdIkIjA688OAmyQLAuUrZTSnsmIZr4JolJhqR3VOHTfytMlpu01J8SkpPuUiRcWvws77NcOa6ONHadnYRvpJqSnORD9et_tuSL-4zdrfxNdhmkYUehbhBrRGj6XdRMw0yrbcP_EGli4VQQ
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Models+and+matheuristics+for+the+unrelated+parallel+machine+scheduling+problem+with+additional+resources&rft.jtitle=European+journal+of+operational+research&rft.au=Fanjul-Peyro%2C+Luis&rft.au=Perea%2C+Federico&rft.au=Ruiz%2C+Rub%C3%A9n&rft.date=2017-07-16&rft.pub=Elsevier+B.V&rft.issn=0377-2217&rft.eissn=1872-6860&rft.volume=260&rft.issue=2&rft.spage=482&rft.epage=493&rft_id=info:doi/10.1016%2Fj.ejor.2017.01.002&rft.externalDocID=S0377221717300073
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=0377-2217&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=0377-2217&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=0377-2217&client=summon