Design and construction progress of BRIF

A new RIB project, the Beijing Radioactive Ion-beam Facility (BRIF), has been running at CIAE since 2004. In this project, a 100 MeV H-cyclotron, CYCIAE-100, is selected as the driving accelerator providing a 75-100 MeV, 200-500 μA proton beam. An ISOL system employs two stage separators to reach th...

Full description

Saved in:
Bibliographic Details
Published inChinese physics C Vol. 34; no. 1; pp. 103 - 111
Main Author 张天爵 关遐龄 崔保群
Format Journal Article
LanguageEnglish
Published IOP Publishing 2010
China Institute of Atomic Energy, Beijing 102413, China
Subjects
Online AccessGet full text
ISSN1674-1137
0254-3052
2058-6132
DOI10.1088/1674-1137/34/1/019

Cover

More Information
Summary:A new RIB project, the Beijing Radioactive Ion-beam Facility (BRIF), has been running at CIAE since 2004. In this project, a 100 MeV H-cyclotron, CYCIAE-100, is selected as the driving accelerator providing a 75-100 MeV, 200-500 μA proton beam. An ISOL system employs two stage separators to reach the mass resolution of 20000. Its RIB beam will be injected into the existing Tandem and a superconducting booster installed down stream of the Tandem will increase the energy by 2 MeV/q. The progress of BRIF, giving special emphasis to CYCIAE-100, will be introduced in this paper.
Bibliography:11-5641/O4
cyclotron, main magnet, RF cavity, ISOL, QWR, superconducting cavity