Advances in the Physical Start-Up Test Program for VVER-1200 Power Units

Unit 1 of the Novovoronezh NPP-2 operating the first VVER-1200 reactor of the 3+ generation reached a critical state for the first time in May 2016, and the physical start-up of the power unit was carried out. The National Research Center Kurchatov Institute was the scientific supervisor of the star...

Full description

Saved in:
Bibliographic Details
Published inPhysics of atomic nuclei Vol. 87; no. 8; pp. 1039 - 1046
Main Authors Tsyganov, S. V., Kraynov, Yu. A., Gribov, A. A.
Format Journal Article
LanguageEnglish
Published Moscow Pleiades Publishing 01.12.2024
Springer Nature B.V
Subjects
Online AccessGet full text
ISSN1063-7788
1562-692X
DOI10.1134/S1063778824080234

Cover

More Information
Summary:Unit 1 of the Novovoronezh NPP-2 operating the first VVER-1200 reactor of the 3+ generation reached a critical state for the first time in May 2016, and the physical start-up of the power unit was carried out. The National Research Center Kurchatov Institute was the scientific supervisor of the start-up of the first-of-a-kind unit with the VVER-1200 reactor at the Novovoronezh NPP-2 and power units of the Belarusian NPP. By now, five VVER-1200 units have been commissioned. The experience gained during the preparation and conduct of physical tests at the first units was used during the start-up of the next ones. Specific features of the preparation and implementation of the program of physical tests at VVER-1200 units, which were developed and implemented by specialists of the National Research Center Kurchatov Institute, are presented.
Bibliography:ObjectType-Article-1
SourceType-Scholarly Journals-1
ObjectType-Feature-2
content type line 14
ISSN:1063-7788
1562-692X
DOI:10.1134/S1063778824080234